Emergency Repair of Kaupakalua Road In the Vicinity of Lepo Street - Phase 1

Project Name

Emergency Repair of Kaupakalua Road in the Vicinity of Lepo Street – Phase1

Project No. 21-48                                            

 

Scope of Work

The project involves shoulder restoration with retaining walls, Construction work includes new paved shoulders and guardrail installation, new concrete walls with soil nails to support the shoulder area, and grading.


Construction activities will start Monday, November 14, 2022 with anticipated completion of late March 2023.  Hours of operation is from 7:00 am to 3:30 pm Monday to Friday except weekends and holidays.  Activities which requires lane closure will be allowed between 8:30 am to 3:00 pm.  At least one lane will be available at all times during work hours.

(Project Map)

 

When

NTP:  November 14, 2022

Contract Working Days:  90

Estimated Completion Date:  Late March, 2023

 

Streets Involved

Kaupakalua Road (In the vicinity of Lepo St.)

 

Contractor

Maui Kupono Builders, LLC dba Manu Builders

309 Kamalei Circle

Kahului, HI 96793

(808) 870-4789

 

Contract Cost

$704,531.00

 

Project Contact

Department of Public Works
 200 South High Street Suite 410
 Engineering Division 
 (808) 270-7745


Construction Update:


Work Completed last Week:  (11/21/22 to 11/25/22)

  • Water filled traffic barriers delivered, installed and filled along edge project’s pavement.
  • Water diversion swale established along Kaupakalua Road.
  • Cleared and grubbed material were removed from project site.
  • Additional perimeter filter socks installed.
  • Gravel and fabric placed on driveway to staging area.

Work Scheduled this Week:  (11/28/22 to 12/02/22)

  • Complete concrete jacket for existing water line.
  • Begin excavation for new retaining wall over and on the sides of the culvert.


(For additional project info. and picture updates, click on the following links.)