Onehee Avenue Roadway Improvements

Project Name

Onehee Avenue Roadway Improvements

FAP No. STP-3960(001)                                

 

Scope of Work

The scope of work consists of pavement reconstruction within the road right-of-way.  The scope of work also includes removal of existing sidewalks, installation of new raised concrete sidewalks and bike lanes, installation of new curb/gutters, removal/replacement of existing curb ramps and driveway aprons, installation of new pavement striping and markers, adjusting manholes/valves frames and covers where needed, removal/replacement of existing drainlines, waterlines and sewer lines, installation of new catch basins and drain manholes, and removal/replacement of signage and posts.  and other incidental items. other incidental items.

(Project Map)


When

Notice to Proceed:  January 5, 2022

Actual Start Date:  February 4, 2022

Contract Working Days:  166

Estimated Completed Date:  March 23, 2023

 

Streets Involved

Onehee Avenue (South Papa Ave. to South Wakea Ave)

 

Contractor

Hawaiian Dredging Construction Company

605 Kapiolani Boulevard

Honolulu, HI 96813

(808) 735-3211

 

Contract Cost

$7,024,500.00

 

Project Contact

Department of Public Works
 200 South High Street Suite 410
 Engineering Division 
 (808) 270-7745


Construction Update:

Work Completed Week of 05/14/23 - 05/20/23:

  • Phase 1 -Wakea St. to Ola St.:  Roadway Open - Punchlist Work Ongoing
  • Phase 2 - Ola St. to Uhu St.: Roadway Open - Punchlist Work Ongoing
  • Phase 3 - Uhu St. to Papa St.:  Roadway Closed 24/7 - Grading Sidewalks & Driveways, Pouring Sidewalks & Driveways, Installing Curb & Gutters-all Ongoing. Installed Drainage. Drainlines-Form/Pour Catch Basins.

Work Scheduled Week of 05/21/23 - 05/27/23:

  • Phase 1 - Wakea St. to Ola St.:  Roadway Open - Punchlist Work Ongoing
  • Phase 2 - Ola St. to Uhu St.: Punchlist Work Ongoing
  • Phase 3 - Uhu St. to Papa St.:  Roadway Closed 24/7 - Grading Sidewalks & Driveways, Pouring Sidewalks & Driveways, Installing Curb & Gutters-all Ongoing. Install Drainage Structures-Ongoing. Drainlines-Form/Pour Catch Basins. Excavate/Grade Subgrade for Bike Path & Parking Areas. Lay UTB for Parking Area.