Onehee Avenue Roadway Improvements

Project Name

Onehee Avenue Roadway Improvements

FAP No. STP-3960(001)                                

 

Scope of Work

The scope of work consists of pavement reconstruction within the road right-of-way.  The scope of work also includes removal of existing sidewalks, installation of new raised concrete sidewalks and bike lanes, installation of new curb/gutters, removal/replacement of existing curb ramps and driveway aprons, installation of new pavement striping and markers, adjusting manholes/valves frames and covers where needed, removal/replacement of existing drainlines, waterlines and sewer lines, installation of new catch basins and drain manholes, and removal/replacement of signage and posts.  and other incidental items. other incidental items.   

(Project Map)


When

Notice to Proceed:  January 5, 2022

Actual Start Date:  February 4, 2022

Contract Working Days:  166

Estimated Completed Date:  October 5, 2022

 

Streets Involved

Onehee Avenue (South Papa Ave. to South Wakea Ave)

 

Contractor

Hawaiian Dredging Construction Company

605 Kapiolani Boulevard

Honolulu, HI 96813

(808) 735-3211

 

Contract Cost

$7,024,500.00

 

Project Contact

Department of Public Works
 200 South High Street Suite 410
 Engineering Division 
 (808) 270-7745


Construction Update:

Work Completed Week of 09/18/22 - 09/24/22:

  • Phase 1 -Wakea St. to Ola St.:  Roadway Closed 24/7 
    • Form/Pour/Finish-Walk Ramps
    • Asphalt Paving for Bike & Travel Lanes
  • Phase 2 - Ola St. to Uhu St.:
    • Excavate/Grade Subgrade for Sidewalks
  • Phase 3 - Uhu St. to Papa St.:
    • No Work

Work Scheduled Week of 09/25/22 - 10/02/22:

  • Phase 1 - Wakea St. to Ola St.:  Roadway Closed 24/7
    • Parking Areas/Guy Anchors/Curbs
    • Asphalt Paving/ Travel Lanes/Striping & Signs
    • Landscaping/Plant Trees/Hydromulch
  • Phase 2 - Ola St. to Uhu St.: 
    • Excavate/Grade Subgrade for Sidewalks
  • Phase 3 - Uhu St. to Papa St.: 
    • No Work