- Home
- Government
- Public Works
- Engineering Division
- Current & Future Projects
- Mill Street Pavement Reconstruction
Mill Street Pavement Reconstruction
Project Name
Mill Street Pavement Reconstruction
North Market Street to Lower Main Street
FAP No. STP-3840(001)
Scope of Work
The project involves the removal of existing pavement down to gravel subbase within the roadway right-of-way and installation of new asphalt concrete pavement section with reinforcing geogrid; removal and widening of existing sidewalks, removal/installation of new curb/gutters, removal/replacement of existing curb ramps and driveway aprons, installation of new pavement striping and markers, adjusting manholes/valves frames and covers where needed, removal/replacement of existing drainlines, removal/replacement of existing catch basins and drain manholes, and removal/replacement of signage and posts. Portion of existing retaining wall along Mill Street will also be removed and replaced with new retaining
wall.
Work days are from Monday to Friday except weekends and holidays with hours of operation from 8:30 am to 3:30 pm. Single lane closure is anticipated throughout the project duration with some intermittent full road closures as the need arises.
When
NTP: February 28, 2022
Contract Working Days: 302
Estimated Completed Date: August 2023
Streets Involved
Mill Street (North Market St. to Lower Main St.)
Contractor
Maui Kupono Builders
309 Kamalei Circle,
Kahului, HI 96732
(808) 870-4789
Contract Cost
$4,101,628.87
Project Contact
Department of Public Works
200 South High Street Suite 410
Engineering Division
(808) 270-7745
Construction Update:
Work Completed Last Week: (05/15/23 to 05/19/23)
- No work scheduled. Project is undergoing design changes to the existing utility system.
Work Scheduled This Week: (05/22/23 to 05/26/23)
- No work scheduled. Project is undergoing design changes to the existing utility system.
The contractor tentatively to return to work in June 2023.
Due to utility conflicts and existing condition of the utility lines, the project is being redesigned for improvements to the Sewer, Water and Drainage systems.
(For additional project info. and picture updates, clink on the following links.)
- 230522 Mill St Pavt Recon Weekly Status Report
- 230515 Mill St Pavt Recon Weekly Status Report
- 230508 Mill St Pavt Recon Weekly Status Report
- 230501 Mill St Pavt Recon Weekly Status Report
- 230424 Mill St Pavt Recon Weekly Status Report
- 230417 Mill St Pavt Recon Weekly Status Report
- 230410 Mill St Pavt Recon Weekly Status Report
- 230403 Mill St Pavt Recon Weekly Status Report
- 230320 Mill St Pavt Recon Weekly Status Report
- 230313 Mill St Pavt Recon Weekly Status Report
- 230306 Mill St Pavt Recon Weekly Status Report
- 230227 Mill St Pavt Recon Weekly Status Report
- 230220 Mill St Pavt Recon Weekly Status Report
- 230213 Mill St Pavt Recon Weekly Status Report
- 230206 Mill St Pavt Recon Weekly Status Report
- 230130 Mill St Pavt Recon Weekly Status Report
- 230123 Mill St Pavt Recon Weekly Status Report
- 230116 Mill St Pavt Recon Weekly Status Report
- 230109 Mill St Pavt Recon Weekly Status Report
- 230102 Mill St Pavt Recon Weekly Status Report
- 221226 Mill St Pavt Recon Weekly Status Report
- 221219 Mill St Pavt Recon Weekly Status Report
- 221212 Mill St Pavt Recon Weekly Status Report
- 221205 Mill St Pavt Recon Weekly Status Report
- 221128 Mill St Pavt Recon Weekly Status Report
- 221121 Mill St Pavt Recon Weekly Status Report
- 221114 Mill St Pavt Recon Weekly Status Report
- 221107 Mill St Pavt Recon Weekly Status Report
- 221031 Mill St Pavt Recon Weekly Status Report
- 221024 Mill St Pavt Recon Weekly Status Report
- 221017 Mill St Pavt Recon Weekly Status Report
- 221010 Mill St Pavt Recon Weekly Status Report
- 221003 Mill St Pavt Recon Weekly Status Report
- 220926 Mill St Pavt Recon Weekly Status Report
- 220919 Mill St Pavt Recon Weekly Status Report
- 220912 Mill St Pavt Recon Weekly Status Report
- 220905 Mill St Pavt Recon Weekly Status Report
- 220829 Mill St Pavt Recon Weekly Status Report
- 220822 Mill St Pavt Recon Weekly Status Report
- 220815 Mill St Pavt Recon Weekly Status Report
- 220801 Mill St Pavt Recon Weekly Status Report
- 220725 Mill St Pavt Recon Weekly Status Report
- 220718 Mill St Pavt Recon Weekly Status Report
- 220711 Mill St Pavt Recon Weekly Status Report
- 220704 Mill St Pavt Recon Weekly Status Report
- 220627 Mill St Pavt Recon Weekly Status Report
- 220620 Mill St Pavt Recon Weekly Status Report
- 220613 Mill St Pavt Recon Weekly Status Report
- 220530 Mill St Pavt Recon Weekly Status Report
- 220523 Mill St Pavt Recon Weekly Status Report
- 220516 Mill St Pavt Recon Weekly Status Report
- 220509 Mill St Pavt Recon Weekly Status Report
- 220502 Mill St Pavt Recon Weekly Status Report
- 220425 Mill St Pavt Recon Weekly Status Report
- 220418 Mill St Pavt Recon Weekly Status Report
- 220411 Mill St Pavt Recon Weekly Status Report
- 220404 Mill St Pavt Recon Weekly Status Report
- 220328 Mill St Pavt Recon Weekly Status Report
- 220321 Mill St Pavt Recon Weekly Status Report
- 220314 Mill St Pavt Recon Weekly Status Report
- 220307 Mill St Pavt Recon Weekly Status Report