Mill Street Pavement Reconstruction

Project Name

Mill Street Pavement Reconstruction

North Market Street to Lower Main Street

FAP No. STP-3840(001)


Scope of Work

The project involves the removal of existing pavement down to gravel subbase within the roadway right-of-way and installation of new asphalt concrete pavement section with reinforcing geogrid; removal and widening of existing sidewalks, removal/installation of new curb/gutters, removal/replacement of existing curb ramps and driveway aprons, installation of new pavement striping and markers, adjusting manholes/valves frames and covers where needed, removal/replacement of existing drainlines, removal/replacement of existing catch basins and drain manholes, and removal/replacement of signage and posts. Portion of existing retaining wall along Mill Street will also be removed and replaced with new retaining

wall.

 Work days are from Monday to Friday except weekends and holidays with hours of operation from 8:30 am to 3:30 pm. Single lane closure is anticipated throughout the project duration with some intermittent full road closures as the need arises.

(Project Map)


When

NTP:  February 28, 2022

Contract Working Days:   302

Estimated Completed Date:   April 2023


Streets Involved

Mill Street (North Market St. to Lower Main St.)


Contractor

Maui Kupono Builders

309 Kamalei Circle,

Kahului, HI 96732

(808) 870-4789


Contract Cost

$4,101,628.87


Project Contact

Department of Public Works
 200 South High Street Suite 410
 Engineering Division
 (808) 270-7745


Construction Update:


Work Completed Last Week:  (09/26/22 to 09/30/22)

  • Drain line cleaning and CCTV..
  • Repair damaged drainline.
  • Investigate exist. waterline.

Work Scheduled This Week:  (10/03/22 to 10/07/22)

  • Demo and build DHM at Imi Kala St..
  • Demo Catch Basin and extend deck.
  • Start demo of existing Sidewalk between Central Ave. and Imi Kala St.