East Maui District Resurfacing (FY2020 & FY2021)

Project Name

East Maui District Resurfacing (FY 2020 & FY 2021)

Project No. 20-12                                            

 

Scope of Work

The project involves the resurfacing of Piilani Highway from Milepost Marker 32 to Milepost 32.75.   The scope of work also involves limited cold planing work to transition to existing pavement, pavement striping and markers, and other incidental items.


Hours of operation will be from 8:30 a.m. to 3:30 p.m. Monday thru Friday except holidays and most weekends.  However, there will be full road closures on two Saturdays (October 16 and October 23, 2021) from 8:30 AM to 4:30 PM

(Project Map)

 

When

NTP:  October 14. 2021

Contract Working Days:   80

Estimated Completion Date:   Middle of February, 2022

 

Streets Involved

Piilani Highway (MP 32 to MP 32.75)

 

Contractor

Maui Paving, LLC

1300 N. Holopono Street, Suite 201

Kihei, HI 96753

(808) 877-2755

 

Contract Cost

$378,685.00

 

Project Contact

Department of Public Works
200 South High Street Suite 410
Engineering Division
 (808) 270-7745