Ali'iolani & Alalani Street Pavement Reconstruction

Project Name


Ali’iolani Street & Alalani Street Pavement Reconstruction
Project No. 20-32


Scope of Work


The project involves reconstructing the roadway pavement section of Ali’iolani Street and Alalani Street in the Pukalani Terrace subdivision. The scope of work also includes speed humps; culvert replacement; centerline monument reconstruction; water valve adjustments; pavement striping and markers; signage installation; and other incidental items.
Work days are from Monday to Friday except weekends and holidays. Hours of operation will be from 8:30 am to 3:30 pm. Single land closure is anticipated throughout the project duration with some intermittent full road closure as the need arises.
(Project Map)

When


NTP:  March 1, 2021
Contract Working Days:  140
Estimated Completion Date:  September 22, 2021

Streets Involved


Alalani Street
Ali’ioilani Street

Contractor


Maui Kupono Builders, LLC
309 Kamalei Circle
Kahului, HI 96732
(808) 870-4789

Contract Cost


$1,513,904.80

Project Contact


Department of Public Works
200 South High Street Suite 410
Engineering Division
(808) 270-7745

Construction Update:



Work Completed Weed of 03/28/21 - 04/03/21:


  • Remove and Replace Drain line on Alalani St.

Work Scheduled Weed of 04/04/21 - 04/10/21


  • Cont. Remove and Replace Drain line on Alalani St.