Kahana Nui Bridge Replacement

Project Name


Kahana Nui Bridge Replacement
FAP No. BR-3080(009)


Scope of Work


The project includes demolition and removal of existing bridge structure footing and abutment walls, existing utilities, landscaping, and concrete curb and gutter, sidewalk and driveways; construction of new asphalt concrete pavement, new concrete gutter, utility improvements, new bridge structure, footing and abutment walls, driveways, sidewalk and curb ramps, signing and striping; and all other incidental work necessary to complete project.

Work days are from Monday to Friday except weekends and holidays. Hours of operation will be from 8:30 am to 3:30 p.1. Single lane closure is anticipated throughout the project duration with some intermittent full road closures as the need arises.
(Project Map)

When


NTP:  February 8, 2022
Contract Working Days: 270
Estimated Completed Date:  Tentative - March 2023

Streets Involved


Lower Honoapiilani Road (between Hua Nui Place and Omaikai Place)

Contractor


Goodfellow Bros. LLC
1300 N. Holopono Street, Suite 201
Kihei, HI 96753
(808) 879-5205

Contract Cost


$5,323,615.90

Project Contact


Department of Public Works
200 South High Street Suite 410
Engineering Division
(808) 270-7745

Construction Update:



Work Completed Last Week:  (06/13/22 to 06/17/22)

  • Continue Waterline A-1 installation within stream and Lower Honoapiilani Road.
  • Pour concrete jacket mauka north and south of stream.

Work Scheduled This Week:  (06/20/22 - 06/24/22)


  • Cleanup project site
  • Install bridge closure and traffic detour message boards and signage.
  • Send out closure notices to EMS, Fire, Police and Maui Bus.

Additional Notes


  • One lane alternating traffic control being utilized.
  • Bridge closure and detour scheduled for July 5.
  • Lane closure hours 8:00 a.m. to 3:00 p.m. (adjusted start time from 8:30 a.m.)
  • Water quality in stream monitored daily and photographs taken weekly.