Kaupakalua Road Pavement Reconstruction - Phase 2

Project Name


Kaupakalua Road Pavement Reconstruction – Phase 2
FAP No. STP-0365(011)


Scope of Work


This project consists of the removal of existing pavement down to the gravel subbase within the road right-of-way, and installing a new asphalt concrete pavement section with reinforcing geogrid. The scope of work also includes installing new pavement striping and markers, replacement of existing water system, adjusting manhole/valves frames and covers where needed, removal/replacement of dented guardrails and removing/replacing signage and posts.

 The hours of operation will be from 8:30 am to 3:30 pm Monday to Friday with one lane alternating traffic, and an anticipated weekend full road closure starting in early December.  Weekend hours will be from 7:00 am Saturday until 6:00 pm Sunday with detour route in place.  There will be no activities on holidays.

 For any questions, please call our Engineering Office at 270-7745 
(Project Map)


When


NTP:  October 5, 2020
Contract Working Days: 304
Estimated Completion Date:  May 2021


Streets Involved


Kaupakalua Road (E. Kuiaha Road to Hana Highway)

Contractor


Maui Paving, LLC
949 Kamokila Blvd., Suite 100
Kapolei, HI 96707
(808) 674-8383

Contract Cost


$5,718,862.80


Project Contact


Department of Public Works
200 South High Street Suite 410
Engineering Division
(808) 270-7745

Construction Update:



Work Completed Last Week of 04/12/21 - 04/16/21:


  • MIsc. utility adjustments St. 117+43 to 278+87 (From project beginning to end)
  • Inclement weather hindered project progress.

Work Scheduled Week of 04/19/21 - 04/23/21:

  • Start installation and replacement of existing signs throughout projects Sta. 117+43 to 278+87 (From E. Kuiaha to end of project)
  • Start Pavement striping Sta. 117+43 to 278+87 (From E. Kuiaha to end of project)
  • Misc. utility adjustments Sta. 117+43 to 278+87 (From E. Kuiaha to end of project)